Phase 1: Construction of the intake and eastern canals, access roads, bridge, culverts, and staging area.
Phase 2: Construction of the 50,600 acre-ft reservoir, including its pump station, spillway, and discharge canal.
Phase 3: Construction of the 6,300 acre storm-water treatment area.